CONSTRUCTION PROGRESS

We continue construction!

Despite the difficult times, work is actively underway at the construction site of the DIADANS residential complex. In almost two months, we managed to finish and start the following works:

1. Monolithic works on the 1st section have been completed. Currently, work is being carried out on the reinforcement and concreting of the vertical and horizontal elements of the technical floor of the 2nd section.  

2. The laying of walls on floors 26-27 of the 1st section and 26-28 floors of the 2nd section has been completed. 

3. We continue work on the stone masonry walls of 28-29 floors of the 1st section and 29 floors of the 2nd section.

4. Installed window structures on the 23rd floor of the 1st and 2nd sections.

5. We continue work on the installation of window structures from the 24th to the 27th floors of the 1st and 2nd sections.

6. Finished work on the construction of the hinged facade: subsystem and minwata - 17th floor; Porcelain stoneware installation - from 8 to 9 floors in 1 and 2 sections.  

7. Also, work is being carried out on the installation of the hinged facade: subsystem and minvata - 18 floors; porcelain stoneware installation - from 10 to 14 floors in 1 and 2 sections.

8. The work on the arrangement of the facade on the ceilings of the balconies of the 23rd floor in both sections has been completed.

9. The work on the arrangement of screeds in apartments and balconies of 21 floors in 2 sections and 19 floors in 1 section has been completed.

10. We continue work on the installation of screeds in apartments and balconies of 23-25 floors in 2 sections and screeds on balconies of 13-16 floors in the 1st section.

11. Work on the installation of the elevator equipment in the stylobate part of the DIADANS residential complex has been completed

12. At present, work is being carried out on the installation of the elevator equipment of two elevators in the 1st section.

13. Work is being carried out on the construction of internal engineering networks from the 15th to the 30th floor in the 1st and 2nd sections.

We work in compliance with all necessary technological and environmental requirements

LIVE STREAM
1 section
2 section
SUBMIT YOUR APPLICATION