CONSTRUCTION PROGRESS

What we managed to do during the construction of DIADANS in September. We report:

1. Reinforcement, concreting of vertical and horizontal elements of the 28th floor (1 section) is underway.

2. Work is underway on the reinforcement, concreting of vertical and horizontal elements of the 29th floor (section 2).

3. Work is underway on the reinforcement, concreting of vertical and horizontal elements of the stylobate part.

4. Work is underway to lay the walls of the facade of 22-24 floors (1 section).

5. Work is underway to lay the walls of the facade of 21-23 floors (section 2).

6. Work is underway on the installation of window structures on floors 20-22 (1 section).

7. Work is underway to arrange window structures on floors 19-23 (section 2).

8. Work is underway to arrange facade lighting.

9. Work is underway to arrange internal engineering communications.

10. Works on the facade arrangement are in progress: installation of mineral wool on the ceilings of balconies on floors 15-16 (section 2) and floors 9-10 (Section 1).

11. Commencement of work on the installation of a cement-sand screed.

12. Work is underway to arrange external engineering networks.

Technical supervision of construction work is carried out on a daily basis at the construction site.

All work is carried out in accordance with the schedule

LIVE STREAM
1 section
2 section
SUBMIT YOUR APPLICATION