CONSTRUCTION PROGRESS

The construction of the DIADANS residential complex continues! We pay special attention to the quality of materials, and the team has been actively working on orders, logistics of finishing materials and their preparation for further installation.

What has already been delivered and is ready for the next stages:

- wide-format tiles for public areas - ordered, manufactured and ready for installation.

- glass fire doors for elevator lobbies - successfully delivered for further installation.

- floor tiles - brought to the site, their installation is already in preparation.

- technical doors on the floors - in the process of logistics to the site.

- facade luminaires — manufactured and ready for the next stages.

What is already in the final stages:

- entrance doors to apartments — are in the production stage.

- glass for the upper floors — ordered and is in the production stage.

Each process — from order to delivery — is thought out and implemented with maximum attention to detail. We continue to confidently move forward to create a space that will exceed your expectations. Follow our updates!

We share the results of the construction progress of the DIADANS housing complex. September 2024.

Facade works:

- Baskets for air conditioners were installed on floors 4 - 14 (1 section).

Roof:

- Work continues on the manufacture and installation of decorative elements of the frame on the roof (1 section).

Engineering networks:

- Work on the installation of internal networks continues. water supply, sewage and heating networks in apartments and common areas (section 1 and 2).

- Work continues on the installation of internal electrical networks (section 1 and 2).

- Work continues on the arrangement of ventilation networks of technical premises (section 1 and 2).

- Work continues on the installation of intra-site water supply and sewerage networks (1 section).

- Work on installation of fire alarm systems continues.

We share the construction progress report for July for the DIADANS residential complex.

Facade work:

- Air conditioner baskets have been installed on the 14th-29th floors (Section 1).

- Tiling work with porcelain tiles on the balconies continues on the 27th-29th floors.

Roofing:

- Work on the manufacture and installation of the frame for the decorative element on the roof continues (Section 1).

Engineering networks:

- Work on the installation of internal water supply, sewage, and heating networks continues (Sections 1 and 2).

- Work on the installation of internal electrical networks continues (Sections 1 and 2).

- Work on the installation of ventilation networks continues (Sections 1 and 2).

- Work on the installation of on-site water supply and sewage networks continues (Section 1).

- Work on the installation of fire alarm systems continues.

Glazing systems:

- Work on the installation of glazing systems on the 30th-31st floors continues (Section 1).

We share the construction progress for June at the DIADANS residential complex.

Facade works:

1. Work has begun on installing air conditioner baskets (Section 1).

Engineering networks:

1. Work continues on the installation of internal water supply, sewage, and heating networks (Sections 1 and 2).

2. Work continues on the installation of internal electrical networks (Sections 1 and 2).

3. Work continues on the installation of ventilation networks (Sections 1 and 2).

4. Work continues on the installation of internal water supply and sewage networks (Section 1).

5. Fire alarm system installation is underway.

Roof:

1. Work continues on the fabrication and installation of the roof frame for the decorative element (Section 1).

2. Work continues on the fabrication and installation of the roof frame for the decorative element (Section 2).

Glazing systems:

1. Work continues on the installation of glazing systems on the 30th-31st floors (Section 1).

Construction continues even during power outages, as a generator is installed on the site.

We are sharing the construction progress for the month of May of the DIADANS residential complex.

Facade works:

1. Finished the installation of porcelain tiles on floors 27-29 (1 section).

Engineering networks:

1. Internal water supply, sewage, and heating network installation works continue (sections 1 and 2).

2. Internal electrical network installation works continue (sections 1 and 2).

3. Ventilation network installation works continue (sections 1 and 2).

4. Works on internal courtyard water supply and sewage networks are in progress (section 1).

Roof:

1. Manufacturing and installation works of the decorative element roof framework continue (section 1).

2. Manufacturing and installation works of the framework for the decorative element on the roof continue (section 2).

Glazing systems:

1. Installation works for glazing systems on floors 30-31 are ongoing (section 1).

Despite power outages, construction continues thanks to the generator, which ensures uninterrupted work.

We are sharing the construction progress for the month of April of the DIADANS residential complex.

Facade works:

1. Installation of ceramic granite tiles continues on floors 27-29 (section 1).

Engineering networks:

1. Internal water supply, sewage, and heating network installation works continue (sections 1 and 2).

2. Internal electrical network installation works continue (sections 1 and 2).

3. Ventilation network installation works continue (sections 1 and 2).

4. Works on internal courtyard water supply and sewage networks are in progress (section 1).

Roof:

1. Manufacturing and installation works of the decorative element roof framework continue (section 1).

2. Manufacturing and installation works of the framework for the decorative element on the roof continue (section 2).

Glazing systems:

1. Installation works for glazing systems on floors 30-31 are ongoing (section 1).

We are working in compliance with all necessary technological and environmental requirements.

Sharing construction updates for the month of March:

Section 1:

1. Completion of installation works for the metal frame and mineral wool insulation for the curtain facade on floors 26-29.

2. Installation works for ceramic granite tiles on floors 27-28 are in progress.

3. Ongoing installation works for internal water supply, sewage, and heating networks.

4. Continuation of works for internal electrical networks installation.

5. Continuation of works for ventilation network installation.

6. Continuation of works for manufacturing and installation of the roof framework for decorative element.

7. Installation works for internal courtyard water supply and sewage networks are in progress.

Section 2:

1. Ongoing installation works for internal water supply, sewage, and heating networks.

2. Continuation of works for internal electrical networks installation.

3. Continuation of works for ventilation network installation.

4. Roof works include manufacturing and installation of the framework for the decorative element.

Sharing construction updates for the month of :February:

Section 1:

1. Installation of the metal frame and mineral wool for the curtain wall façade on floors 26-29 continues.

2. Installation of ceramic granite tiles on floors 27-28 is in progress.

3. Work on internal water supply and sewage networks continues.

4. Completion of screed work on the 25th floor.

5. Screed work on the 26th floor is ongoing.

6. Work on internal electrical networks continues.

7. Installation of ventilation networks is ongoing.

8. Production and installation of the roof frame for the decorative element on the roof continues.

Section 2:

1. Installation of glass panes on floors 28-29 is completed.

2. Work on internal water supply and sewage networks continues.

3. Work on internal electrical networks continues.

4. Installation of ventilation networks is ongoing.

5. Work on the production and installation of the frame for the decorative element on the roof continues.

Sharing construction updates for the month of January:

Section 1:

1. Installation of the metal frame and mineral wool for the curtain facade on floors 26-29 is ongoing.

2. Ceramic granite tile installation is in progress on floors 27-28.

3. Internal water supply and sewage network installation works are ongoing.

4. Screed pouring is underway on the 25th floor.

5. Installation of internal electrical networks continues.

6. Ventilation network installation works are ongoing.

7. Fabrication and installation of the roof framework decorative element are in progress.

Section 2:

1. Installation of double-glazed windows on floors 28-29 is in the final stages.

2. Installation works for internal water supply and sewage networks are ongoing.

3. Installation of internal electrical networks continues.

4. Ventilation network installation works are ongoing.

5. Fabrication and installation of the roof framework decorative element are in progress on the roof.

Starting the year 2024 with construction updates for December:

Section 1:

1. Completed installation of double-glazed windows on the 29th floor.

2. Ongoing installation of a metal frame and mineral wool for the curtain wall on floors 26-29.

3. Completed installation of ceramic granite tiles on floors 23-26.

4. In progress: installation of internal water supply and sewage networks.

5. Continuing work on internal electrical installations.

6. Ongoing installation of ventilation networks.

7. Working on manufacturing and installing the framework for the decorative roof element.

Section 2:

1. Continuing installation of double-glazed windows on floors 28-29.

2. Completed installation of the metal frame for the curtain wall and mineral wool on the 27th floor.

3. Ongoing installation of the metal frame for the curtain wall and mineral wool on floors 28-29.

4. Completed installation of ceramic granite tiles on floors 26-29.

5. Completed installation of the elevator equipment for the last two passenger elevators.

6. In progress: installation of internal water supply and sewage networks.

7. Continuing work on internal electrical installations.

8. Ongoing installation of ventilation networks.

9. Working on manufacturing and installing the framework for the decorative roof element on the roof.

Section 1:

1. Completed installation of double-glazed windows on the 28th floor.

2. Currently installing double-glazed windows on the 29th floor.

3. Work is in progress for the installation of a metal frame and mineral wool for the curtain wall on floors 26-29.

4. Installation of ceramic granite tiles is in progress on floors 23-25.

5. Internal plumbing and sewage network installation is in progress.

6. Installation of internal electrical networks is in progress.

7. Installation of ventilation networks is in progress.

8. Completed roofing and engineering equipment installation.

Section 2:

1. Completed installation of double-glazed windows on the 27th floor.

2. Currently installing double-glazed windows on the 28th and 29th floors.

3. Work is in progress for the installation of a metal frame for the facade and mineral wool for the curtain wall on floors 27-29.

4. Installation of ceramic granite tiles is in progress on floors 26-28.

5. Continued installation of elevator equipment for two passenger elevators.

6. Internal plumbing and sewage network installation is in progress.

7. Installation of internal electrical networks is in progress.

8. Installation of ventilation networks is in progress.

9. Completed roofing and engineering equipment installation.

Section 1:

1. Installation of double-glazed windows is in progress on the 28th floor.

2. Work is underway to install a metal frame and mineral wool for the suspended facade on the 26th floor.

3. Installation of ceramic granite tiles is in progress on the 23rd floor.

4. Work is being carried out for the installation of internal water supply and sewage networks.

5. Work is being carried out for the installation of internal electrical networks.

6. Work is being carried out for the installation of ventilation networks.

7. Installation work for the roof and engineering equipment is ongoing.

Section 2:

1. Roof and engineering equipment installation work has been completed.

2. Installation of double-glazed windows is in progress on the 28th floor.

3. Work is underway to install a metal frame for the facade and mineral wool for the suspended facade on floors 27-29.

4. Installation of ceramic granite tiles is in progress on floors 26-27.

5. Elevator equipment installation continues.

6. Work is being carried out for the installation of internal water supply and sewage networks.

7. Work is being carried out for the installation of internal electrical networks.

8. Work is being carried out for the installation of ventilation networks.

Section 1:

1. The installation of double-glazed windows from the 25th to the 27th floor has been completed.

2. Installation of double-glazed windows from the 28th to the 29th floor is underway.

3. The installation of the metal frame and mineral wool for the hinged facade on the 24th and 25th floors has been completed.

4. Work is underway to install a metal frame and mineral wool for the hinged facade on the 26th floor.

5. The installation of porcelain tiles on the 22nd floor has been completed.

6. Installation of porcelain tiles on the 23rd floor is underway.

7. Work is underway to install waterproofing, screeds, and ceramic granite on the floors of the balconies on the 28th and 29th floors.

8. Installation of elevator equipment continues.

9. Work on the arrangement of internal engineering networks is underway.

Section 2:

1. The installation of double-glazed windows from the 25th to the 26th floor has been completed.

2. Work is underway to install double-glazed windows on the 27th and 29th floors.

3. The installation of the metal frame and mineral wool for the hinged facade from the 24th to the 26th floor has been completed.

4. Work is underway to install a metal frame and mineral wool for the hinged facade on the 27th and 29th floors.

5. Work is underway to install waterproofing, screeds and ceramic granite on the floors of the balconies on the 28th and 29th floors.

6. The installation of porcelain tiles on the 25th floor has been completed.

7. Installation of porcelain tiles from the 26th to the 27th floor is underway.

8. Installation of elevator equipment continues.

9. Work on the arrangement of internal engineering networks is underway.

1. Installation of double-glazed windows is being carried out from the 25th to the 27th floors in the 1st and 2nd sections.

2. Work is underway to install the metal frame of the facade on the 24th and 25th floors of the 1st and 2nd sections.

3. We are proceeding with the installation of elevator equipment in the 1st and 2nd sections.

4. Work is in progress to insulate and finish balcony ceilings from the 26th to the 29th floors in the 1st and 2nd sections.

5. Work is ongoing to install subsystems and mineral wool for the exterior facade from the 24th to the 25th floors of the 1st and 2nd sections.

We are working while adhering to all necessary technological and ecological requirements.

1. Masonry works are being carried out on the technical floor of the 1st and 2nd sections.

2. Installation of glass panels is underway on floors 27 to 29 in the 1st and 2nd sections.

3. Insulation and decoration of balcony ceilings on the 25th floor of the 1st and 2nd sections have been completed.

4. Installation of subsystem and mineral wool on the ventilated facade is in progress on the 25th and 27th floors (1st section).

5. Installation of subsystem and mineral wool on the ventilated facade is in progress on the 27th and 29th floors (2nd section).

6. Ceramic granite is being laid on the 22nd and 23rd floors (1st section).

7. Ceramic granite is being laid on the 26th floor (2nd section).

8. Works are ongoing for the insulation layer of the roof in the 1st and 2nd sections.

9. Continuing the installation of elevator equipment in the 1st and 2nd sections.

We are working in compliance with all necessary technological and environmental requirements.

1. Masonry work is being carried out on the technical floors of both sections.

2. Installation of glass units is underway on floors 24 to 27 in both sections.

3. Insulation and finishing of balcony ceilings from the 26th to 27th floors in the 1st and 2nd sections have been completed.

4. Insulation and finishing of balcony ceilings on the 28th floor in the 1st and 2nd sections are in progress.

5. Installation of the subsystem and mineral wool for the curtain facade is being done on the 25th and 26th floors in the 1st section and on the 20th and 29th floors in the 2nd section.

6. Ceramic granite installation is underway on the 23rd floor in the 1st section and on the 18th floor in the 2nd section.

7. The roof insulation layer is being installed in the 1st and 2nd sections.

8. We work in compliance with all necessary technological and environmental requirements.

1. The work on the masonry of the walls on the technical floor of both sections has been completed.

2. Window installation is in progress on the 24th and 27th floors of both sections.

3. The insulation and finishing of balcony ceilings on the 24th and 25th floors in the 1st and 2nd sections have been completed.

4. Work on the insulation and finishing of balcony ceilings on the 27th floor in the 1st and 2nd sections is in progress.

5. The installation of the subsystem and mineral wool for the curtain facade is underway on the 23rd and 24th floors of the 1st section and from the 17th to the 29th floors of the 2nd section.

6. The installation of ceramic granite continues on the 22nd floor of the 1st section and the 17th floor of the 2nd section.

7. Work on the installation of the insulating layer of the roof are being carried out in the 1st and 2nd sections.

8. We work in compliance with all necessary technological and environmental requirements.

1. The monolithic works in both sections have been completed.

2. The installation of ceramic granite has been completed from the 8th to the 9th floors in both sections. The installation of ceramic granite continues from the 10th to the 14th floors in both sections.

3. Work on window construction has been completed on the 23rd floor in both sections.

4. The insulation and finishing of balcony ceilings on the 23rd floor in the 1st and 2nd sections have been completed.

5. The masonry of walls on the 26th and 27th floors in the 1st section and on the 26th and 28th floors in the 2nd section has been completed.

6. Also, work on the installation of the curtain facade, including the subsystem and mineral wool, has been finished on the 17th floor in both sections.

7. Currently, work on the installation of the curtain facade, including the subsystem and mineral wool, is in progress on the 18th floor in both sections.

8. We are working in compliance with all necessary technological and ecological requirements.

1. The monolithic works in the 1st section have been completed. Currently, works are underway on the reinforcement and concreting of vertical and horizontal elements of the technical floor in the 2nd section.

2. The masonry of walls on the 26th and 27th floors in the 1st section and on the 26th and 28th floors in the 2nd section has been completed.

3. We continue the stone-masonry work on the 28th and 29th floors in the 1st section and the 29th floor in the 2nd section.

4. Windows have been installed on the 23rd floor in both the 1st and 2nd sections.

5. We continue the installation of windows from the 24th to the 27th floors in both the 1st and 2nd sections.

6. The installation of the curtain facade has been completed on the 17th floor, including the subsystem and mineral wool, and the installation of ceramic granite from the 8th to the 9th floors in both the 1st and 2nd sections.

7. Also, work is in progress on the installation of the curtain facade on the 18th floor, including the subsystem and mineral wool, and the installation of ceramic granite from the 10th to the 14th floors in both the 1st and 2nd sections.

8. The facade work on the balcony ceilings of the 23rd floor has been completed in both sections.

9. The finishing of the floors and balconies on the 21st floor in the 2nd section and the 19th floor in the 1st section has been completed.

10. We continue the floor finishing and balcony work from the 23rd to the 25th floors in the 2nd section, and the balcony work from the 13th to the 16th floors in the 1st section.

11. The installation of elevator equipment in the stylobate part of the DIADANS residential complex has been completed.

12. Currently, work is underway on the installation of elevator equipment for two elevators in the 1st section.

13. Internal engineering network works are being carried out from the 15th to the 30th floors in both the 1st and 2nd sections.

14. We are working in compliance with all necessary technological and ecological requirements!

1. We have completed the reinforcement and concreting of all elements on the 30th floor of the first section and the 31st floor of the second section. Work is ongoing on the 31st floor of the first section and the technical floor of the second section.

2. The masonry of the facade walls for the 26 floors in both the first and second sections has been completed.

3. We are continuing the construction of facade walls on the 27th floor of the first section and starting on the 27th floor of the second section.

4. Window installations have been completed on the 21st floors of both the first and second sections, and the work continues on the 22nd and 23rd floors.

5. We have installed internal engineering communications on the 22nd floor of both sections, and the installation of external engineering networks is in progress.

6. Cement-sand screeds have been completed on the 22nd floors of both sections, and ventilated facades have been installed on the 14th floors of both the first and second sections.

7. We are currently installing facade lighting on the premises.

8. We are working in compliance with all necessary technological and ecological requirements..

1. The work on reinforcement and concreting of the elements of the 30th floor of the 1st section and the 30th floor of the 2nd section was completely completed. We continue work on the 31st floor.

2. The masonry of the walls of the facades of the 25th-26th floors of the 1st section and 23-25th of the second section has been completed. Work continues on the 27th floor of the 1st and 26-27th of the 2nd.

3. Window structures were installed on the 20th floors of both sections. We continue work on the 21st-23rd floors of the 1st-2nd sections.

4. Facade lighting and internal engineering communications are being installed.

5. On the ceiling of the balconies of the 15th-16th floors of two sections, mineral wool is mounted.

6. A cement-sand screed has been installed on the 15th–19th floors of both sections, and work is ongoing on the 20th–21st floors.

7. Reinforcement work continues and we are concreting the elements of the stylobate part.

8. External utility networks are being installed and work has begun on installing the ventilated facades of the 1st and 2nd sections.

9. We work in compliance with all necessary technological and environmental requirements.

1. The reinforcement and concreting of the elements of the 29th floor of the 1st section and the 29th floor of the 2nd section have been completed. Work continues on the 30th floors of both sections.

2. Elements of the stylobate part are reinforced and concreted

3. The masonry of the facade walls of the 23rd–25th floors of the 1st section and 20–23rd of the 2nd floor has been completed. On the 25th-27th floors of the 1st section and on the 24th-25th floors of the 2nd, work continues.

4. Window structures were installed on the 17th-19th floors of the 1st section and on the 19th floor of the 2nd. Work continues on the 20th floors of both sections.

5. Mineral wool is laid on the ceiling of the balconies of the 15th-16th floors of the 2nd section.

6. A cement-sand screed is installed on the 15th-19th floors of both sections.

7. Facade lighting, internal and external engineering communications are installed.

8. Installation of the ventilated facade in two sections has begun.

9. We work in compliance with all necessary technological and environmental requirements.

1. Reinforcement and concreting of the elements of the 28th floor of the 1st section, the 29th floor of the 2nd section and the stylobate part continued.

2. Next, the facade walls of the 22nd–24th floors of the 1st section and the 21st–23rd floors of the 2nd section will be laid.

3. Window structures are being installed on the 20th–22nd floors of the 1st section and on the 19th–23rd floors of the 2nd section.

4. Installation of facade lighting, internal engineering communications, and external engineering networks continues.

5. Mineral wool is installed on the ceilings of the balconies on the 15th and 16th floors of the 2nd section and on the 9th and 10th floors of the 1st.

6. The laying of the cement-sand screed has begun.

7. We work in compliance with all necessary technological and environmental requirements.

1. Reinforced and concreted the 26th–27th floors of the 1st section and the 28th floor of the 2nd section; work continues on the 28th floor of the 1st, on the 29th floor of the 2nd, and on the stylobate part;

2. The walls of the facade on the 18th–19th floors of the 1st section and on the 19th–20th floors of the 2nd section have been laid on the 19th–23rd floors of the 1st and on the 21st–23rd floors of the 2nd, work is ongoing;

3. Window structures have been installed on the 15th–17th floors of the 1st section and on the 15th–16th floors of the 2nd, on the 18th–19th floors of the 1st and on the 17th–19th floors of the 2nd, work continues;

4. Work continues on the installation of facade lighting and internal engineering communications, Mineral wool is installed on the ceiling of the balconies of the 9th and 10th floors of the 2nd section;

5. The installation of external engineering networks has begun.

6. We work in compliance with all necessary technological and environmental requirements.

1. In July, work on the reinforcement and concreting of vertical and horizontal elements of the 25th floor of the 1st section and the 27th floor of the 2nd section was completed.

2. The masonry of the facade walls of the 14th–17th floors of the 1st section and the 17th–18th floors of the 2nd section was completed.

3. Window structures were installed on floors 11–14 of the 1st section and 10–14 floors of the 2nd section.

4. Work on reinforcement, concreting of vertical and horizontal elements of the 26th floor of the 1st section, the 28th floor of the 2nd section, and the stylobate part continues.

5. The construction of the facade walls of the 18th–22nd floors of the 1st section and the 19–20 floors of the 2nd section is ongoing. Window structures are being installed on floors 15–19 of the 1st section and 15–16 floors of the 2nd.

6. Facade lighting and internal engineering communications are being arranged. Mineral wool is mounted on the ceilings of the balconies.

7. We work in compliance with all necessary technological and environmental requirements.

SUBMIT YOUR APPLICATION