Construction progress
In this section you can independently track the dynamics of building of your home from anywhere in the world. So the distance between us will not become an obstacle and you will not have to re-plan your schedule.
Here you will find actual information about the performed work, live-broadcast and monthly photo reports.

Photo report
Once a month, we publish photo reports on the construction progress – you may follow the process of your residential block construction.
Live streams
DIADANS CONSTRUCTION REPORT AS OF NOVEMBER, 2020
DIADANS CONSTRUCTION REPORT AS OF OCTOBER, 2020
construction
DIADANS CONSTRUCTION REPORT AS OF AUGUST, 2020
DIADANS CONSTRUCTION REPORT AS OF AUGUST, 2020
DIADANS CONSTRUCTION REPORT AS OF JULY, 2020
DIADANS CONSTRUCTION REPORT AS OF JUNE, 2020
DIADANS CONSTRUCTION REPORT AS OF MAY, 2020
DIADANS CONSTRUCTION REPORT AS OF APRIL, 2020
1. Completed work on the reinforcement, concreting of vertical and horizontal elements of the 4th floor (1 section).
2. Work is underway on the installation of horizontal elements of the 5th floor (1 section).
3. Completed work on the reinforcement, concreting of vertical and horizontal elements of the 4th floor (section 2).
4. Work is underway on the reinforcement, concreting of vertical and horizontal elements of the 5th floor (section 2).
Technical supervision of the construction work is carried out on a daily basis at the construction site.
All work is proceeding according to the schedule.
DIADANS CONSTRUCTION REPORT AS OF MARCH, 2020
1. Completed work on the reinforcement of the vertical elements of the 1st floor (1 section).
2. Work is underway to reinforce the vertical elements of the 2nd floor (1 section).
3. We finished waterproofing works (1, 2 sections - underground part).
4. Completed work on the reinforcement of the vertical elements of the 2nd floor (2nd section).
5. Work is underway to reinforce the vertical elements of the 3rd floor (section 2).
Technical supervision of the construction work is carried out on a daily basis at the construction site.
All work is proceeding according to the schedule.
DIADANS CONSTRUCTION REPORT AS OF FEBRUARY, 2020
1. Completed work on the reinforcement of vertical elements on the 1st floor (section 1).
2. Work is underway to reinforce the vertical elements of the 1st floor (1st section).
3. Waterproofing works are underway (1, 2 sections)
4. Completed work on the reinforcement of vertical elements of the 1st floor (2nd section).
5. Work is underway to reinforce the vertical elements of the 2nd floor (2nd section).
Technical supervision of the construction work is carried out on a daily basis at the construction site. All work is proceeding according to the schedule.
DIADANS CONSTRUCTION REPORT AS OF DECEMBER, 2019
1. Completed work on the reinforcement of vertical elements on the 2nd floor (section 1).
2. Work is underway to reinforce the vertical elements of the 1st floor (section 1).
3. Waterproofing works are underway (1, 2 sections).
4. Completed work on the reinforcement of vertical elements of the 1st floor (section 2).
5. Work is underway to reinforce the vertical elements of the 1st floor (2nd section).
Technical supervision of the construction work is carried out on a daily basis at the construction site.
All work is proceeding according to the schedule.
DIADANS CONSTRUCTION REPORT AS OF DECEMBER, 2019
DIADANS construction report as of December, 2019
1. Completed work on the foundation (1 section).
2. Work is underway to reinforce the vertical elements of the 2nd floor (1 section).
3. Waterproofing works are underway (1, 2 sections).
4. Work is underway to reinforce the vertical elements of the 1st floor (section 2).
Technical supervision of the construction work is carried out on a daily basis at the construction site. All work is proceeding according to the schedule.
DIADANS CONSTRUCTION REPORT AS OF OCTOBER, 2019
1. Completed work on the construction of the foundation for the tower crane (section 2).
2. Completed work on the construction of the pile field (1 section).
3. Waterproofing works are underway.
4. Finished the reinforcement of the grillage slab (section 1).
5. Work is underway to arrange formwork, reinforcement of floor slabs (section 2).
6. Work is underway to reinforce vertical structures.
7. The work on pouring the foundation slab has been completed (section 1).
Technical supervision of the construction work is carried out on a daily basis at the construction site. All work is being done according to the schedule.
DIADANS Construction Report as of October, 2019
1. Completed work on the construction of the pile field (section 2).
2. Completed work on the construction of foundations (section 2).
3. Completed installation of a tower crane (section 1).
4. Work is underway to build the foundation for the tower crane (1 section).
5. Work is underway to insrallate the pile field (1 section).
6. Waterproofing works are underway.
Technical supervision of the construction work is carried out on a daily basis at the construction site. All work is proceeding according to the schedule.
DIADANS Construction Report
• Earthwork on the first section is completed.
• Foundation under the tower crane finished (section 1).
• Arrangement of the pile field has begun (section 1).
• Part of the work on the field arrangement has been completed (section 2).
• Foundation work has begun (section 2).
• Waterproofing work has begun.
Technical supervision of construction work is made on everyday basis.
All work is done according to the schedule.
construction
• Excavation work is carried out on section 1.
• Works on the installation of piles under a tower crane were completed.
• The installation of a pile field work is continuing (2 section).
Technical supervision of the construction work is carried out on everyday basis.
All work is carried out in accordance with the schedule.
DIADANS Construction Site Performance Report
• Excavation works on section 2
• Excavation work on section 1 began
• Tower crane piles are mounted
• Fieldworks started (section 2)
Technical supervision of construction work is made on everyday basis.
All work is done according to the schedule.
construction
• Construction of piles of the pit work is done
• Jet piles work is done
• Digging works are ongoing
Technical supervision of construction work is made on a everyday basis.
All work is done according to the schedule
construction
• Dismantling completed
• Excavation for pilot piles completed
• Piles are being tested
Technical supervision of construction work is carried out on a everyday basis.
All work is done according to schedule